Hause Gill

100kW, Cumbria
A 100kW high head project on Hause Gill, Seatoller. This scheme is being developed by the National Trust, with Ellergreen providing the consenting works.
Site: Hause Gill
Consenting timeline: Jan 2015– Dec 2015
Construction timeline: 2016-2018
Commissioning date: September 2018
Location: Lake District
Turbine: Turgo
Generator: Synchronous
Intake type: Coanda screen
Gross head: 144.5m
Catchment area: About 1.3km2
Max turbine flow: 97lps
Max output: 100kW
Penstock length: ~1km