Mill Beck Old Hutton
60kW, Cumbria
A 60kW low/med head project to provide a dependable income stream on a farm
| Site: | Mill Beck Old Hutton |
|---|---|
| Consenting timeline: | Sept 2011 – December 2013 |
| Construction timeline: | 2013-2015 |
| Commissioning date: | June 2015 |
| Location: | Lake District |
| Turbine: | Ecowave Crossflow |
| Generator: | 3 phase asynchronous generator |
| Grid: | 3 Phase, 80kVA PMT |
| Intake type: | Coanda Screen |
| Gross head: | 15m |
| Catchment area: | 16.8km2 |
| Max turbine flow: | 750lps |
| Max output: | 60kW |
| Pipeline length: | 290m |