Stickle Ghyll, Langdale
100kW, Langdale, Cumbria
A 100kW project in Langdale, Lake District, working closely with the National Trust.
| Site: | Stickle Ghyll, Langdale |
|---|---|
| Consenting timeline: | Nov 2012 – Dec 2013 |
| Construction timeline: | 2014-2015 |
| Location: | Lake District |
| Turbine: | Gilkes Turgo 13.5″ |
| Generator: | 122kVA Induction |
| Grid: | 200kVA transformer |
| Intake type: | Half height Coanda screen |
| Gross head: | 77 metres |
| Catchment area: | 2.4 km2 |
| Max turbine flow: | 0.184m3/s |
| Max output: | 100 kW |
| Pipeline length: | 160 metres |