Anderton Hydro Scheme
22kW, Northwich
A low head 22kW micro hydro scheme on the site of the Anderton Boat lift.
Site overview
| Site: | Anderton |
|---|---|
| Construction timeline: | June 2019 – 2020 |
| Commissioning date: | 2019 |
| Location: | Northwich |
| Turbine: | Crossflow |
| Intake type: | Tyrolean |
| Gross head: | 15m |
| Catchment area: | – |
| Max turbine flow: | 240lps |
| Max output: | 22kW |