Crosby Gill
100kW, Cumbria
A low head 100kW micro hydro scheme on Crosby Gill.
Site overview
| Site: | Crosby Gill |
|---|---|
| Construction timeline: | June 2019 – 2020 |
| Commissioning date: | 2019 |
| Location: | Crosby Gill |
| Turbine: | Turgo |
| Intake type: | Coanda |
| Gross head: | 100m |
| Catchment area: | 9 km2 |
| Max turbine flow: | 137lps |
| Max output: | 100kW |