Logan Gill

450kW, Cumbria
A 450kW project in the Lake District’s Duddon Valley
Site: Logan Gill
Design surveys: September 2008 – January 2009
Consenting timeline: March 2009 – August 2009
Construction timeline: August 2009 – July 2010
Commissioning date: July 2010
Location: Lake District
Turbine: Gilkes Turgo Impulse
Generator: 1000 rpm Asynchronous
Grid: 526kVA dedicated sub-statio
Intake type: Coanda
Gross head: 96m
Catchment area: 8.4km2
Max turbine flow: 600lps
Max output: 450kW
Pipeline length: 1050m