Yew Beck
5kW, Cumbria
A domestic scale 5kW scheme near Rusland, Cumbria. This scheme is being aided by Ellergreen through the design & consenting phase.
| Site: | Yew Beck |
|---|---|
| Consenting timeline: | May 2012– Dec 2013 |
| Construction timeline: | 2014-2015 |
| Commissioning date: | October 2015 |
| Location: | Rusland, Cumbria |
| Turbine: | Turgo |
| Generator: | tbc |
| Intake type: | Coanda screen |
| Gross head: | 11.24m |
| Catchment area: | About 1.14km2 |
| Max turbine flow: | 62lps |
| Max output: | 5kW |
| Penstock length: | 71m |